2/7/2011 - Notice to Proceed - Issued
4/15/2011 - Draft Baseline Hydrology Report - Completed
6/7/2011 - Final Baseline Hydrology Report - Completed
8/25/2011 - Draft Alternatives Evaluation Report - Completed
12/20/2011 - Final Alternatives Evaluation Report - Completed
2/1/2012 - Select Best Alternative Plan - Completed
3/26/2012 - Draft Conceptual Design Report - Completed
5/8/2012 - Final Conceptual Design Report - Completed
1/23/2012 - Draft Flood Hazard Area Delineation - In Review