Schedule

2/7/2011 - Notice to Proceed - Issued

4/15/2011 - Draft Baseline Hydrology Report - Completed

6/7/2011 - Final Baseline Hydrology Report - Completed

8/25/2011 - Draft Alternatives Evaluation Report - Completed

12/20/2011 - Final Alternatives Evaluation Report - Completed

2/1/2012 - Select Best Alternative Plan - Completed

3/26/2012 - Draft Conceptual Design Report - Completed

5/8/2012 - Final Conceptual Design Report - Completed

1/23/2012 - Draft Flood Hazard Area Delineation - In Review