Date - Milestone

7/27/2010 - Notice to Proceed - Issued

 

9/1/2010 - Draft Baseline Hydrology Report - Completed

 

10/25/2010 - Final Baseline Hydrology Report - Completed

12/8/2010 - Draft Alternatives Evaluation Report - Completed


12/1/2010 - Draft Digital Flood Hazard Area Delineation - Completed


2/7/2011 - Final Alternatives Evaluation Report - Completed

 

2/7/2011 - Final Digital Flood Hazard Area Delineation - Completed

 

3/21/2011 - Select Best Alternative Plan - Completed


6/27/2011 - Draft Conceptual Design Report - Completed


9/06/2011 - Final Conceptual Design Report - Completed