Date - Milestone
7/27/2010 - Notice to Proceed - Issued
9/1/2010 - Draft Baseline Hydrology Report - Completed
10/25/2010 - Final Baseline Hydrology Report - Completed
12/8/2010 - Draft Alternatives Evaluation Report - Completed
12/1/2010 - Draft Digital Flood Hazard Area Delineation - Completed
2/7/2011 - Final Alternatives Evaluation Report - Completed
2/7/2011 - Final Digital Flood Hazard Area Delineation - Completed
3/21/2011 - Select Best Alternative Plan - Completed
6/27/2011 - Draft Conceptual Design Report - Completed
9/06/2011 - Final Conceptual Design Report - Completed